Assign people to tasks
Choose who does each task, seeing skill and free hours.
For: admins, project managers.
- In the Skill column, choose the skill the task requires (optional, but it helps find the right person).
- In the Resources column, click + (Assign to…). The list shows the people with that skill and the free hours per day of each one in the task's period.
- Hover over or open the person's calendar to see free days, days they do not work and days they are already full.
- Choose the person. If it works, they appear on the task. If not, UProject tells you the day and the reason.
- To remove someone, click the x next to the name.
Resources are assigned to tasks, not to summary tasks. A person can be assigned to a task that requires a skill only if they have that skill.
Tip: To see at a glance the workload of the whole team across all projects, use Resource allocation.