Blocking of over-allocation and time conflicts
How UProject prevents someone from being in two places at once or going over the hour limit.
This is one of UProject's core features. Instead of only showing over-allocation after it has happened, UProject prevents the assignment at the moment the PM tries to make it, and explains why.
What is blocked
- Over-allocation: the person would go over the daily hour limit, adding up all projects (default 8h). Message: “Over the limit on [day]”.
- Time conflict: the person is already on another task, in any project, at the same time. Message: “Busy on [day], [task and time]”.
- Day not available: the task falls on a weekend, holiday or the person's time off. Message: “Not working on [day]”.
The block applies everywhere hours change: when assigning in the table, when changing the hours of a day in the Work tab, when changing a task's dates and when you Save schedule.
Times calculated from the work
- When you change a task's work, UProject calculates the start and finish times: each person does, per day, at most the daily limit times their percentage (40% of 8h = 3h12, for example from 08:00 to 11:12).
- The task goes to the first free slot of the people on it that day. When you assign someone who is already busy at that time, the task moves to after what is already scheduled, if it fits in the day.
- The reverse also holds: changing the finish to a part-of-day time (e.g. 08:00 to 10:00 for 5 days) changes the work to that time multiplied by the days (10h).
- A time conflict is any overlap, even if the percentages add up to less than 100%. Tasks that came from MS Project stay as they are until you touch their work, dates or people.
On the Allocation screen, each task shows its time next to the name, and days with a time conflict appear outlined in red (on the person, the project and the task). Hover to see the clashing time.
When saving the schedule
If, after changing dates, someone ends up in two places at once or on a day that is not available, the save is refused with an explanation. When the problem is the day, the button Move to the next working day and recalculate appears, which moves the tasks and lets you check before saving again.
How to make an exception
- Working on a weekend or holiday: the admin opens Settings › Resources, edits the person and, under Released days, enters the date and the hour limit for that day.
- More than 8h in a day: also under Released days, with a higher limit (up to 24h). Hours above 8 count from 17:00.
- Change the limit for everyone: Settings › Settings, Resources tab, Daily hour limit.
Turning on and off
Both blocks come on by default. The admin can turn each one off in Settings › Settings, Schedules tab:
- Block over-allocation off: the assignment is accepted, and the Allocation screen shows the day in red.
- Block time conflicts off: the person can be on two tasks at the same time.
Tip: We recommend keeping both on. That way the saved schedule can always be carried out with the people on it.