Blocking of over-allocation and time conflicts

How UProject prevents someone from being in two places at once or going over the hour limit.

This is one of UProject's core features. Instead of only showing over-allocation after it has happened, UProject prevents the assignment at the moment the PM tries to make it, and explains why.

What is blocked

The block applies everywhere hours change: when assigning in the table, when changing the hours of a day in the Work tab, when changing a task's dates and when you Save schedule.

Times calculated from the work

On the Allocation screen, each task shows its time next to the name, and days with a time conflict appear outlined in red (on the person, the project and the task). Hover to see the clashing time.

When saving the schedule

If, after changing dates, someone ends up in two places at once or on a day that is not available, the save is refused with an explanation. When the problem is the day, the button Move to the next working day and recalculate appears, which moves the tasks and lets you check before saving again.

How to make an exception

Turning on and off

Both blocks come on by default. The admin can turn each one off in Settings › Settings, Schedules tab:

Tip: We recommend keeping both on. That way the saved schedule can always be carried out with the people on it.