S-curve: planned × actual

See whether the project is moving as planned, day by day.

For: admins, project managers, viewers.

On the project screen, right below Earned value, the S-curve shows how much of the budget (cost, or hours when there is no cost) should have been done and how much has been done, over time.

Tip: The past comes from the schedule's saved versions (the most recent ones): each Save stores the tasks' % for that day. Before the oldest version it cannot be reconstructed; from the first record on, one point per day is added. Consultants, and anyone without the See costs permission, do not see the S-curve.