S-curve: planned × actual
See whether the project is moving as planned, day by day.
For: admins, project managers, viewers.
On the project screen, right below Earned value, the S-curve shows how much of the budget (cost, or hours when there is no cost) should have been done and how much has been done, over time.
- Planned (dashed line): comes from the active baseline; without a baseline, from the schedule's current dates.
- Actual (solid line): it is each day's earned value, stored every day from the first day the project was recorded.
- The Today line marks the current day. Below the chart appear today's planned and actual values.
Tip: The past comes from the schedule's saved versions (the most recent ones): each Save stores the tasks' % for that day. Before the oldest version it cannot be reconstructed; from the first record on, one point per day is added. Consultants, and anyone without the See costs permission, do not see the S-curve.