Cross-project dependencies

When a task in this project waits for a task in another project.

For: admins, project managers, viewers.

  1. In the Cross-project dependencies block, choose the task in this project.
  2. Choose the other project, its task and the link type: FS (only starts when the other finishes), SS, FF or SF.
  3. Write a note, if you like, and click Add.

The block shows what this project waits for and which projects wait for it, with the situation: on time, delivered, late or task removed. If the other project misses the date, the health indicator turns yellow. The dates are those of each project's saved schedule.