Project health indicator
How the health indicator is calculated and how to adjust it.
The health indicator is calculated automatically from the company's rules. Next to it appear the reasons, such as:
- Finish after the contract date or the baseline.
- % complete below what is expected for today.
- Late tasks or tasks past their deadline.
- Open high risks or issues, decisions stalled for more than 7 days and overdue dependencies.
- Tasks from other projects that delay this one.
- Forecast cost above the contract value or delivery below spending (CPI).
The health indicator also shows open items: project without a PM, without a baseline, without an update for 14 days or without resources.
Adjust the health indicator
The PM can click Adjust health, choose the color and write the reason. The project list shows that the health was adjusted and what the calculated one was. Choose Automatic to go back to the rules.
Tip: The limits for green, yellow and red are in Settings › Settings, Portfolio tab (admin).