Freeze the approved plan and measure how far the project has slipped.

A baseline is a snapshot of the approved plan's dates. With it, UProject shows each task's variance and the health indicator knows whether the schedule has slipped.

  1. Click Baselines.
  2. Choose the number (from 0 to 10) and write the reason (e.g. plan approved by the client).
  3. Click Save baseline. If the number already exists, UProject asks whether you want to replace it.
  4. In Compare with, choose the baseline used in the table, the Gantt and the health indicator. It can also be the one that came from the imported file.

Use the columns Start (baseline), Finish (baseline), Duration (baseline) and Variance (working days between the baseline finish and the current one: + slipped, − ahead).