Upload a new version of the file

Update an imported project with a new file from MS Project or another tool.

For: admins, project managers.

  1. In the project, click Upload new version and choose the file.
  2. UProject shows what changes before applying it: new tasks, removed tasks, tasks with changed dates and renamed tasks.
  3. It also warns what will be lost: tasks created on the platform, edits made here and assignments made here. Click see which to see the names.
  4. If everything looks right, click Apply new version.

Warning: The file wins: tasks, dates, dependencies and assignments become the file's. The Skill, the columns created in UProject, the PM and the column order stay. To avoid losing what was done here, export the schedule first.

Tip: If the file looks like it is from a different schedule, UProject warns you. Check before applying.