Works: quantity measurement
Measure construction progress in m², meters or units, not only in %.
The construction module is contracted separately: the UProject owner turns it on for your company. When it is on, the project screen gains the Works: quantity measurement block.
Define the quantity (admin and the project's PM)
- In the works block, click Quantity on the task row.
- Enter the unit (m², m, un...), the planned quantity and the unit price, and save.
Measure
- Click Measure on the task row, enter the date, the quantity executed and, if you like, a note.
- A measurement by the project's PM (or the admin) goes in already approved. Measurements by other people stay pending until the PM clicks Approve (or Reject).
The approved measurement becomes the task's %: measured quantity ÷ planned quantity, at most 100%. This % outranks hours and the typed %, and feeds earned value and the S-curve with no extra setup. The measured value is the measured quantity × the unit price.
Warning: When you define a task's quantity, its % starts following the measurements only. With no approved measurement, the % is 0.
Measurement bulletin
In Measurement bulletin, choose the period and click Show bulletin to see, per task, what was measured in the period and the accumulated total, in quantity and in currency.
Tip: Those with the Measure works permission enter measurements; those with Approve measurements (and who are the project's PM) approve. The admin sets this up in the user categories.
Site diary
- Just below, in Works: site diary, choose the day (it cannot be in the future).
- Enter the weather in the morning and afternoon, the workforce by role, the equipment and the occurrences. Tasks with an approved measurement on that day appear by themselves.
- Click Save diary. When the day is complete, click Sign and lock the day: it can no longer be edited.
- Only the project's PM (or the admin) can Reopen the day. Use Print or save as PDF to produce the day's sheet.
Those with the Measure works permission fill in the diary; those who only see the project can only read.
Physical-financial schedule
For those with the See costs permission, the Works: physical-financial schedule block shows, month by month, the planned (each task's expected value spread across the baseline dates) and the actual (approved measurements × unit price), with the cumulative curves and the variance. Only tasks that have a planned quantity are included. Use Download as Excel to take the table away, including by schedule group.