Recalculate schedule
Redo dates, slack and the critical path.
For: admins, project managers.
Recalculate schedule redoes the dates, slack and critical path using the predecessors, constraints and calendars. Use it when the imported file came without being recalculated or after many changes.
- Click Recalculate schedule.
- See how many tasks change date, and which ones.
- Click Apply and then Save schedule.