Edit tasks in the table
Insert, move, indent, copy, bulk-edit and link tasks.
For: admins, project managers.
Edit a field
Click the field (name, duration, start, finish, % complete, predecessors, constraint, deadline, skill or one of your own columns) and type. When you change dates, duration or predecessors, the schedule recalculates by itself.
- The dates of a summary task come from the tasks inside it: change the tasks, not the summary.
- Predecessors: use the row number, the type and the lag, such as `3`, `3SS` or `4FF+2d`. Types: FS (finish-to-start, the default), SS (start-to-start), FF (finish-to-finish) and SF (start-to-finish).
- Constraint type: as soon as possible, must start on, finish no later than, and so on. The constraint date appears next to the type and can be changed there.
- Deadline: if the finish goes past it, the task appears in the check and weighs on the health indicator.
Task menu (right-click)
- Insert task below: enter the name and the duration in working days.
- Indent (becomes a subtask of the task above) and Outdent (moves up one level).
- Copy, Paste below and Duplicate.
- Mark as complete (becomes 100%) and Reopen task.
- Bulk edit… and Delete.
Warning: Only tasks created on the platform can be deleted. Those that came from an imported file go away when you upload a new version of the file without them.
Move and select
- Drag a row by the handle on the left to change its position.
- Tick the boxes on the left to select several tasks and use Bulk edit to give the same value to a field on all of them (leaving it empty clears the value).
- Show level opens and collapses the summary tasks at once, on the Table, Gantt and Work screens: Level 1 shows only first-level summaries, collapsed; Level 2 opens those and shows the second-level ones collapsed, with each one's summary; Show all, the last option, opens everything. The arrow next to a name opens or collapses just that summary task.
Tip: Changes stay as Unsaved changes until you click Save schedule. See Saving and versions.