Work tab: hours per day
See and change each person's hours on each day, planned and actual.
The Work tab (like MS Project's “Task Usage”) shows each task with the assigned people below it and the hours of each day alongside.
- Show: Work (planned), Actual work (logged and approved hours) or Both.
- Period: choose the start date and how many weeks appear; use Previous week and Next week to move.
- Columns: choose the columns on the left (Id, Duration, Start, Finish, % complete, Work, Actual and Remaining).
- Change hours (PM and admin): click the person's cell for the day and type the hours. Putting hours on a day outside the dates changes the task's start or finish. The over-allocation and conflict blocks apply here too.
- Right-clicking a task opens the same menu as the table (insert, copy, paste, delete, scroll to the task).
Tip: In large schedules, the tab loads tasks gradually. Use Load more or Load all.