Earned value
The project's schedule and cost in numbers: PV, EV, AC, SPI and CPI.
The Earned value block compares what should have been done, what was done and what was spent. With costs in the schedule, the calculation is in money; without costs, in hours.
- PV (planned value): how much should already be done, by the baseline dates (or the current ones, if there is no baseline).
- EV (earned value): what was done (budget × % complete).
- AC (actual cost): the larger of the schedule's actual cost and the approved hours × each person's hourly cost.
- SPI = EV ÷ PV: above 1, ahead; below 1, behind.
- CPI = EV ÷ AC: above 1, earning more than was spent; below 1, spending more than was delivered.
- EAC: estimate at completion (budget ÷ CPI), and VAC, the variance at completion.
The block also shows how much of the budget has been consumed, the spending per month and for how many months the balance lasts.
Tip: Who sees costs depends on the category's See costs permission.