The points of attention found and the DCMA quality score.

In the Schedule check block, UProject lists the problems found, with severity (error, warning or information) and a link to go to the task.

Quality score (DCMA)

The score from 0 to 100 uses the schedule quality criteria adopted by PMOs (DCMA 14-point): logic, leads, lags on links, link types, hard constraints, slack, long tasks, invalid dates, tasks without resources, tasks late against the baseline, the baseline execution index (BEI), the critical path test and the CPLI. Hover over each criterion to see what it measures.

Tip: Schedules with more than 400 tasks go without these two tests, because the simulation takes long.