Company rules
The settings for schedules, resources and portfolio.
For: admins.
Settings › Settings holds the rules that apply to all projects. Click Save on each tab.
Schedules
- Work with start and finish times on tasks: unchecked, dates are days only.
- Task durations are whole days only: there is no 1.5 day.
- Recalculate dates with the platform engine on import.
- Split tasks longer than one day into one task per day: the task becomes a summary task with one task per day, with the same time and the same people.
- Block over-allocation and Block time conflicts (they come on). See Blocking of over-allocation and time conflicts.
Resources
- On import, link the file's resource to whoever has the same name and add to Resources the names that do not exist yet.
- Logged hours need the PM's approval: unchecked, the entry goes in already approved.
- Daily hour limit (default 8h): applies to the over-allocation block and to Allocation.
- User categories. See Categories and permissions.
Customizations
The Customizations tab (in Settings › Customizations) has three blocks. Each has a Hide button, and UProject remembers the choice in this browser:
- Schedule columns: columns that appear in all of the company's schedules, alongside each project's own columns. Whoever edits the schedule fills in the values.
- Project fields: extra fields that appear in Project details, in all projects, and serve as filters in the project list. Whoever edits the project fills them in.
- Client fields: extra fields for the client register. They appear in the form and on the client record, and list fields serve as filters in the client list. Whoever edits the client (admin and PM) fills them in.
In each block, New creates the item: give it a name and choose the type (Text, Number, Date, Yes/No or List, with one option per line). Once created, you can change the name and the list options, but not the type. When you delete, the values already filled in are also erased. The company's plan limits how many items you can create (default 20), in each block separately. Only the admin creates, changes and deletes.
Show only when
In project fields and client fields, a field can appear only when another list field in the same block has certain values. When creating or editing the field, under Show only when, choose the list field and check one or more options. Example: the Infrastructure field only appears when Business area is IT.
- The field appears and disappears instantly, depending on the option chosen in the list. The value of a hidden field is not stored and does not enter the filters.
- There is only one level: a conditional field cannot control another, and a field that controls others cannot be conditional.
- If you remove from the list an option used in the rule, it leaves the rule; if none remain, the field starts to always appear. Deleting the list field also frees the fields that depended on it.
- To always show the field, choose Always show.
Security
- Require two-step verification: everyone in the company starts typing, after the password, a code sent to their email. Each computer can be remembered for 30 days. Off (default), each person decides in My account.
Portfolio
- Days late on the finish before turning red: up to that number, yellow; more than that, red.
- Points of % behind schedule for yellow and for red.
- Presentation template: upload the company's .pptx (up to 5 MB, no macros) and the status report presentations come out with its theme, fonts and layouts. The health colors do not change, and slides that are inside the template are not included. You can see which one is in use, download the current one and go back to the UProject default.
- Presentation slides: on the same card, tick which slides go in and use the arrows to change the order, with or without an uploaded template. The project cover and at least one content slide are required. In the portfolio, you can remove the cover and the overview. Restore default returns to the original order.