Import a schedule
Bring in schedules from MS Project, Primavera P6, Excel or CSV.
For: admins, project managers.
- In the top bar, open Projects and click Import schedule.
- Choose the file type and drag the file into the window (or click to choose).
- Check the Import options (explained below) and click Import.
- Read the summary: how many tasks, dependencies, resources and fields came in, and the points of attention found during the check. Click Open project.
Accepted file types
- MS Project (.xml): in MS Project, use File › Save As › XML Format. It brings tasks, dates, predecessors, resources, fields, baseline and calendars.
- Spreadsheet (.csv): Excel or Google Sheets saved as CSV, one task per row, with the columns Name, Level, Start, Finish, Duration (days), Predecessors, Resources and % complete. Use Download a sample spreadsheet to see the format.
- Excel (.xlsx): the first sheet of the workbook, with the same columns as the CSV.
- Primavera P6 (.xer): in P6, use File › Export › Primavera PM (XER). The WBS becomes summary tasks, and activities, milestones, predecessors with lag and resources come in.
Warning: The .mpp file is not accepted. In MS Project, save as XML and upload the .xml. The limit is 50 MB.
Import options
- Link resources to people with the same name: links each resource in the file to the person in Resources (or to the user) with the same name, ignoring accents and capitals.
- Add missing names to Resources: names that do not exist become people, without a login.
- Whole-day durations only: 1.5 days becomes 2 days and the dates are recalculated.
- Keep task times: unchecked, tasks take up whole days.
- Recalculate dates with the platform engine: unchecked, the file's dates are kept.
The default for these options comes from the company rules (Settings › Settings, Schedules and Resources tabs).
Tip: To update an existing project with a new file, do not import again: use Upload new version inside the project. See Upload a new version of the file.