PM guide: from schedule to status report
The step-by-step of a project, from creation to weekly follow-up.
For: admins, project managers.
Build the schedule
- Open Projects in the top bar and choose Import schedule (if you already have the file) or New schedule (to start from scratch). See Import a schedule and Create a schedule from scratch.
- If the company has a template for this type of project, use Copy from a template to bring in the ready-made tasks.
- In the table, adjust names, durations, dates and predecessors. See Edit tasks in the table.
- In Project details, check the PM, the client and the contract fields.
Assign the team
- In the Resources column, click + on the task and choose the person. The list shows who has the requested skill and how many free hours per day each person has.
- If the person is already on another task at the same time or would go over the daily limit, UProject refuses and explains why. See Blocking of over-allocation and time conflicts.
- To adjust the hours of each day, use the Work tab. See Work tab.
Save and freeze the plan
- Click Save schedule. Each save becomes a version with date and time. See Saving and versions.
- When the client approves the plan, save a Baseline with the reason. From then on, the table and the health indicator show how far the project has slipped. See Baselines.
Follow up every week
- In Tasks › Approve hours, approve or reject the hours logged by the team. See Approve hours.
- In the project, record risks, issues and decisions on the RAID board and write an Update (what moved forward, what got stuck and the next steps). See Risks, actions, issues and decisions.
- Check the Health indicator and its reasons. See Project health.
- Generate the weekly Status report and copy it into an email or Teams. See Status report.